DCAA Compliance· · 10 min read
Does My Company Need to Be DCAA Compliant? A Test by Contract Type and Agency
Whether your company needs a DCAA-compliant accounting system depends on the contract type, the agency that funds it, and whether you are the prime or a subcontractor. A plain-English test, with the rule behind each answer.

Most small contractors first hear about DCAA (the Defense Contract Audit Agency, which audits contractors for the Department of Defense) from a solicitation, a prime contractor's questionnaire, or another business owner. The question that follows is simple: does this apply to my company? The answer decides whether you can keep your current setup or need to change how you record time and costs before your next bid.
This guide gives you a test you can run on your own contracts. It is for owners and bookkeepers of small companies that sell, or plan to sell, to the federal government.
The short answer
Your company needs an accounting system the government considers adequate when it holds, or bids on, one of these: a cost-reimbursement contract, a time-and-materials (T&M) or labor-hour contract, or a fixed-price contract with progress payments based on the costs you incur. A firm-fixed-price contract won on competition, with no cost-based financing, generally does not come with an accounting system review.
The answer comes from three questions, in this order:
- 1What type of contract is it?This decides most of the answer. Cost-reimbursement, T&M, labor-hour and cost-based progress payments call for an adequate accounting system.
- 2Who funds it?DCAA audits for the Department of Defense (DoD, now also called the Department of War). Other agencies use DCAA only when they ask for it.
- 3Are you the prime or a subcontractor?Cost-type and T&M subcontracts carry the same audit clause as the prime contract.
"DCAA compliant" is a shorthand. DCAA does not certify companies or software. It checks whether your accounting system is adequate for the type of contract you hold.
The test by contract type
The contract type sets the rule, because it decides how you get paid. On a fixed price, the government pays the agreed price. On a cost-reimbursement contract it pays the costs you document, so your books become the evidence behind every invoice.
| Contract type | Is your accounting system tested? | The rule behind it |
|---|---|---|
| Cost-reimbursement (for example, cost-plus-fixed-fee) | Yes. The contracting officer must be satisfied your system can segregate and accumulate the contract's costs before award, and the government can audit the costs you claim during and after the contract | FAR 16.301-3; FAR 52.215-2(b); at DoD, DFARS 252.242-7006 |
| Time-and-materials or labor-hour | Yes, mainly for labor. Each hour billed has to be supported by a timesheet, and DCAA performs floor checks (unannounced employee interviews) at contractors with this kind of work | FAR 52.215-2(b); at DoD, DFARS 252.242-7006; DCAA Manual 7641.90 |
| Fixed price with progress payments based on costs | Yes. Progress payments are approved only if the accounting system and controls can administer them | FAR 32.503-3; at DoD, DFARS 252.242-7006 |
| Firm-fixed-price, competitively awarded, no cost-based financing | Generally no accounting system review | None of the clauses above apply |
The terms in the table, briefly: the FAR (Federal Acquisition Regulation) is the rulebook for all federal contracts, and the DFARS (Defense Federal Acquisition Regulation Supplement) adds the Defense Department's rules on top. DFARS 252.242-7006, "Accounting System Administration," goes into DoD solicitations and contracts that are cost-reimbursement, incentive, T&M or labor-hour, or that pay progress payments based on costs (DFARS 242.7503).
One exception reaches fixed-price work too. On a negotiated contract above $2.5 million without adequate price competition, you may have to submit certified cost or pricing data (FAR 15.403-4), and DCAA can be asked to audit the proposal. That is an audit of your price, not of your accounting system, but your books still have to support the numbers.
Since July 15, 2026, fixed price is the government's default contract type. Under the updated FAR Part 16, it is the contracting officer who has to document why a different type is used, and that justification addresses whether the contractor's accounting system is adequate. A fixed-price award adds no accounting system review, although a contracting officer can still ask for cost information to decide whether a price is reasonable. Is Fixed-Price the New Default for GovCon Contracts? covers the change.
What "adequate" means
For a cost-reimbursement contract, the FAR condition is that your accounting system can adequately segregate, accumulate and allocate the costs of the contract. Before award, the contracting officer can ask DCAA to evaluate it against the SF-1408 (the government's preaward survey form for a prospective contractor's accounting system). In practice, that means direct costs kept apart from indirect costs, costs tracked by contract, daily timekeeping, unallowable costs excluded, and costs posted at least monthly. The DCAA Pre-Award Accounting System Review walks through each criterion.
The test by agency
- Department of Defense contracts. DCAA is the audit agency. Since a law enacted in December 2025, products and services from nontraditional defense contractors (companies with no recent contract under full Cost Accounting Standards coverage) are exempt from some requirements, including DFARS 252.242-7006, unless the contracting activity applies them in writing. The FAR condition for cost-reimbursement contracts still applies. Is DCAA Going Away? covers what changed.
- Civilian agency contracts. According to DCAA's Information for Contractors manual, DCAA audits costs on non-DoD contracts only when the agency requests it, on a reimbursable basis, and some agencies do not request it. The FAR rules are the same, so a cost-reimbursement contract from a civilian agency still needs an adequate accounting system, whoever audits it.
- Grants. Grants follow their own rules. A nonprofit follows the Uniform Guidance (2 CFR 200), and agencies such as the National Institutes of Health (NIH) and the National Science Foundation (NSF) do not rely on DCAA to review their awardees. If you hold SBIR awards (Small Business Innovation Research), Do SBIR Awardees Need a DCAA-Compliant Accounting System? gives the answer by agency.
Prime or subcontractor
Being a subcontractor does not take you out of scope. The prime contract's Audit and Records clause (FAR 52.215-2) has to be included in subcontracts above the simplified acquisition threshold (the dollar limit for simplified purchasing, defined in FAR 2.101) that are cost-reimbursement, incentive, T&M, labor-hour or price-redeterminable, or that require certified cost or pricing data. Under that clause, the government can examine the records behind the costs you claim on your subcontract.
On a firm-fixed-price subcontract, the clause generally does not flow down. Primes can still ask about your accounting and timekeeping before they team with you, as we cover in Do You Need to Be DCAA-Compliant Before You Win a Contract?
Run the test on your own contracts
If the answer is "not yet"
A company with only firm-fixed-price work does not need to pass an accounting system review today. Two habits still pay off. Recording time by contract and keeping costs by contract shows you whether each fixed-price job makes money, which matters more as agencies shift toward fixed price, as we explain in Is Fixed-Price the New Default for GovCon Contracts?. And the same records are what a contracting officer will look for if your next opportunity is cost-type, often before the award. Building them a few months ahead is far easier than building them during a proposal deadline.
How WiseCost fits
If the test says your company needs to prepare for DCAA, WiseCost is DCAA timekeeping and labor distribution software for small government contractors that keep their books in QuickBooks Online. It covers the labor side of an adequate accounting system, which is where most of the requirements land, without replacing QuickBooks Online:
- Daily timekeeping by contract. Employees record time every day against each contract or indirect account, supervisors approve timesheets, and every change keeps an audit trail.
- The timesheet controls auditors expect. The DCAA preset blocks future-dated entries, makes submitting the timesheet the employee's certification, and requires a different approver.
- Labor cost by contract. Labor distribution posts each contract's labor cost to QuickBooks Online as a journal entry, every pay period.
- Indirect rates from your books. The Indirect Rate report calculates fringe, overhead and G&A (general and administrative) rates from the accounts you assign to each pool.
For a company with only fixed-price work today, the same setup shows labor cost by contract now and gives you a system that is ready when cost-type work comes.
FAQ
The Bottom Line
Look at the contract type first. Cost-reimbursement, T&M and labor-hour contracts, and fixed-price contracts with cost-based progress payments, all require an accounting system the government considers adequate. Then check the agency, since DCAA audits for DoD and only on request for others, and your role, since cost-type and T&M subcontracts carry the same audit clause. If your work is only firm-fixed-price today, start recording time and costs by contract anyway: the records you need for a cost-type contract take time to build. If your books are in QuickBooks Online, WiseCost adds the daily timekeeping, labor cost by contract and indirect rates that DCAA looks for, so you can prepare without changing accounting systems.
Not sure whether your system would pass? Take the free DCAA Readiness Self-Assessment, or start a 14-day free trial of WiseCost on your own QuickBooks Online.
Official Sources
- FAR overhaul Part 16, including 16.301-3 (cost-reimbursement contracts)
- FAR 52.215-2, Audit and Records, Negotiation
- FAR 32.503-3, Initial progress payments
- FAR 15.403-4, Requiring certified cost or pricing data
- DFARS 242.7503, prescription for 252.242-7006, Accounting System Administration
- DCAA Manual 7641.90, Information for Contractors (November 2023)